Phase 3 of Build Belleville postponed
By Isaiah Mawhinney and Emilie Quesnel
BELLEVILLE – City council has decided to delay Phase 3 of the Build Belleville downtown rehabilitation project due to limited funding.
The budget for the project as a whole is $21 million, but Phase 1 of the three planned phases has already cost over half that.
With only $8.1 million remaining, city staff said they knew they couldn’t complete Phases 2 and 3 without going over budget.
Phase 2 will be tendered in January 2016 while Phase 3 has been postponed until alternative funding becomes available.
QNet News talked to Build Belleville co-ordinator Elisha Purchase as well as downtown businesses about the impact and future of the project.
For more information about the project, visit the Build Belleville website.